Quantified schedule.

A quantified schedule combines the itemised work list of a schedule with measured quantities and estimated costs. It shows what needs to be done, how much of it, how long it will take, and what it should cost.

Who this guide is for

Contractors preparing detailed estimates for design and build projects, quantity surveyors managing cost plans, and project teams who need a cost-linked programme.

What a quantified schedule contains

Each work item has: description, quantity, unit, estimated cost per unit, total cost, planned start and finish dates, and responsible trade or subcontractor. The schedule can be sorted by work section or by programme phase, making it useful for both estimating and site management.

Miniature example

Strip existing roof coverings — 90 m² — £8.50/m² — £765 — Week 1
New roof structure — 90 m² — £65.00/m² — £5,850 — Weeks 2–3
Roof covering — 90 m² — £48.00/m² — £4,320 — Week 4
Each item links the quantity, cost, and programme duration.

Common mistakes

  • Adding programme dates without verifying the labour output assumptions
  • Using a quantified schedule when a simple programme or cost estimate alone would suffice
  • Not updating the schedule when costs or programme dates change